BIOKIT (Barcelona)

Turnkey project in Barcelona for the Werfen-Biokit group in its new Lliça d'Amunt laboratories, where we design and execute all of the facilities. This work has white rooms, containment and a room for lyophilizers. The installation of cold rooms is also carried out. This building is made in compliance with the FDA and will obtain LEED certification.

Installations:

Climatization:
Cold production plant with 4,250 KW with three air-cooled condensers of 1,419 kw each.
Heat production plant with 1,992 kW with three boilers of 635 kw and one of 87 kw.
Air conditioning made by air conditioning, fancoils with airflow in air conditioners of 555,000 m3 / h.
Centralized management system, as well as associated electrical installation.

Steam:
Steam production plant 2,210 kg / h with two boilers of 1,105 kg / h each.

Mechanical:
Installation of plumbing, sanitation and sanitation assembly.
Production of ACS by boiler.
Installation of firefighting by bias, preaction, wet and dry sprinklers in addition to automatic extinctions.
Central Osmotized Water Production and Distribution.
Installation of 22 cold rooms (one of them of 3,200 m3).
Installation of HPW / purified water for 98 points of consumption

Special installation:
Installation of medical gases of oxygen and vacuum.

Special installation in white rooms:
Installation of 36 cleanrooms (ISO 8) and 14 containment rooms, 4 climate rooms, a room for lyophilizers.

Electrical installations:
Electrical installation in high voltage and low voltage with four transformation centers of 6,400 KVA in total. Fire detection system and emergency lighting.
Photovoltaic installation.
Communication system and integral telecommunications system.