948 570 029 | 941 247 030 - adisgrup@adisgrup.com

Hospital San Juan de Dios de Pamplona (Pamplona)

Construction of a new building and renovation of the original. Building recognized by the Príncipe de Viana Institution as a protected architectural building. With the new building, the hospital went from 67 to 120 rooms, mostly for individual use. In addition, the Center has a new Rehabilitation Unit of 600 m2 for patients admitted, as well as 8 new operating rooms for the Surgical Block: 5 major ambulatory surgery and 3 minor surgery. It has an underground car park with a capacity of 167 places and the implementation of energy saving and efficiency systems.

Installations:

Climatization:
Air conditioning made using fancoils, radiators, direct expansion equipment, radiators and air conditioners with an air flow of 260,000 m3 / h.
Cold production plant with 3,600 kW (3 air-cooled chillers)
Heat production plant of 2,500 kW (3 boilers).
9 kW electric and 20 kW thermal cogeneration equipment.
309 fancoils in four-pipe installation.
Centralized management system.

Mechanical:
Installation of cold water plumbing and domestic hot water production.
Installation of fire protection.
Sanitation installation.

Special installation in quirophanes:
Air-conditioning of 8 operating rooms with humidity and pressure control.

Special installation:
Installation of medical gases, oxygen and vacuum.